The Texas Department of Transportation is still working on expanding US Highway 75 and the work continues this week to reconstruct the entrance and exit ramps and the bridges at Taylor and Lamberth Streets as well as the US 75 mainlanes over US 82.
This week, they will also be working to reconstruct the frontage road intersection of US 75 at State Highway 91.
“A reduced speed limit of 60 mph on the US 75 mainlanes has been set for this construction project,” the release said. “Two lanes on the US 75 main lanes will remain open in each direction during the daytime hours with occasional further lane closures during the nighttime period. Watch for lane closures on the frontage roads during construction.”
Drivers who frequent these areas are advised to be aware of signage in construction zones.
“These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues,” the release said. “Motorists are advised to remain alert and pay special attention to all signs, barricades, and traffic controls, and reduce their speed as they approach and travel through work zones. They should also avoid distractions such as cell phones, eating, drinking, or car audio or navigation systems.”
The following projects are planned for the week ahead:
Grayson County:
US 75, from the Collin County Line to FM 902. This project will widen the US 75 mainlanes from the Collin County Line to FM 902 to six lanes. The project will also reconstruct the bridge at County Line Road and construct new u-turn bridges in Van Alstyne near Simmons Loop and in Howe south of Hall Cemetery Road. This project will convert the frontage roads from two-way operation to one-way operation. Two lanes on the US 75 main lanes will remain open in each direction during the daytime hours with occasional lane closures during the nighttime period. Watch for lane closures on the frontage roads during construction. A reduced speed limit of 65 mph on the US 75 mainlanes has been set for this construction project.
The US 75 frontage road u-turns at the US 82 frontage road intersection are closed to traffic to allow crews to begin work on a portion of the new US 75 mainlane bridge over US 82. During this closure, traffic is asked to go through the US 75 and US 82 frontage road intersection by making a series of left turns.
The northbound US 75 frontage road exit to SH 91 is closed to allow for construction of the pavement of the new US 75 frontage road intersection with SH 91. During this closure, traffic is asked to stay on the northbound frontage road to Taylor Street and take Taylor Street back to SH 91.
Eastbound and westbound US 82 will have a left lane closure to allow for construction of drilled shafts and columns for the new US 75 bridge over US 82. Traffic should expect delays as US 82 will be reduced to one lane.
The northbound and southbound frontage road from Taylor Street to SH 91 (Texoma Parkway) will be reduced to one lane to allow for construction of the new intersection. An all-way stop will be in place at the southbound US 75 frontage road intersection with SH 91 (Texoma Parkway) to control traffic. Westbound SH 91 traffic is reduced to one lane and will be required to stop at the southbound US 75 intersection.
The westbound SH 91 access to US 75 northbound frontage road will be closed to facilitate the next phase of construction in this area. Northbound motorists intending to access eastbound
SH91 will need to take the N. Travis St Exit (Exit 60), follow the frontage road to Taylor St, turn right and follow Taylor St to SH91. A detour sign will be posted to guide traffic.
The southbound frontage road to northbound frontage road U-Turn at SH 91 will be closed to facilitate the next phase of construction in this area. US 75 Southbound frontage road motorists intending to access the US 75 northbound frontage road will need to continue to N. Travis St, and utilize the U-Turn at Travis St. A detour sign will be posted to guide traffic.
The US 75 northbound exit to SH-91 will be closed to facilitate the construction of the ultimate ramp connection. Motorists intending to access SH-91 will be required to take Exit 60 for N. Travis Street/Taylor Street. Detour signs will be posted along the frontage road at N. Travis Street, Taylor Street, and N Loy Lake intersections.
The US 75 northbound and southbound will have alternate lane closures for mobile operations. This is a moving lane closure that will last for short duration at each location. This closure is scheduled from July 07 to August 02 from 8:00 PM to 5:00 AM.
US 82 eastbound and westbound lanes at the intersection of US 75 and US 82 will have alternate closures for mobile operations. This is a moving lane closure that will last for short duration at each location. This closure is scheduled from July 07 to August 02 from 9:00 PM to 5:00 AM
US 75, from US 82 to North Loy Lake Road. This project will rebuild and widen the US 75 mainlanes from four lanes to six lanes as well as reconstruct the entrance and exit ramps on US 75. The project will also reconstruct bridges at FM 691, Iron Ore Creek and Spur 503, and add U-turn bridges at Loy Lake Road in Sherman and Spur 503 in Denison. A reduced speed limit of 65 mph on the US 75 mainlanes has been set for this construction project. Watch for shoulder closures and lane shifts on the mainlanes of US 75 as well as frontage road lane closures within the project. Watch for nighttime lane closures on the northbound and southbound US 75 mainlanes, as crews work to construct the new pavement section.
Westbound Spur 503 is closed to traffic near US 75 as the overpass to southbound US 75 has been removed to allow for construction of the new overpass. During this closure traffic on westbound Spur 503 will be required to detour onto the frontage road at the temporary exit ramp west of Theresa Drive and continue along the frontage road to the Loy Lake Road intersection where traffic can make the U-turn to continue south on the US 75 frontage road to the entrance ramp before the FM 691 intersection.
The U-turn lanes for the US 75 frontage roads at FM 691 are closed to traffic to allow crews to work on constructing the middle portion of the new US 75 bridge over FM 691. During this closure traffic wishing to make a U-turn at the intersection is asked to turn left onto FM 691 and make another left at the next signal light.
The exit ramp from northbound US 75 to North Loy Lake Road in Denison is closed permanently. Travelers who wish to access North Loy Lake Road from northbound US 75 will detour up to Crawford Street, make a U-turn at the Crawford Street intersection, and head south on the frontage road to reach North Loy Lake Road.
The westbound Spur 503 ramp to northbound US 75 is closed to traffic. A temporary detour is in place to divert this traffic onto the frontage road. Traffic will exit Spur 503 onto the frontage road using the new detour, continue along the Spur 503 frontage road which runs into the US 75 frontage road to the Loy Lake Road intersection. Traffic can continue along the frontage road through Loy Lake Road and then take the next entrance ramp to northbound US 75.
US 75 all southbound lanes will be closed from Iron Ore Creek to FM 691 from July 10 to July 11 from 9;00 PM to 5:00 AM. Traffic need to follow the detour in place.
FM 691 east and westbound lanes will be closed under US 75 overpass from July 10 to July 11 from 9;00 PM to 5:00 AM. Traffic will have to take the frontage road as a detour.
US 75, from FM 1417 to SH 91 (Texoma Parkway). A reduced speed limit of 60 mph on the US 75 mainlanes has been set on the mainlanes for this construction project. Watch for shoulder closures and occasional lane closures on the northbound and southbound US 75 main lanes between SH 91 and FM 1417 as crews work on completing the remaining work on this project. Watch for occasional lane closures on the frontage roads between FM 1417 and SH 91.
US 75 Overlay, from near FM 84 to the Oklahoma State line. Watch for lane closures on northbound and southbound US 75 as crews will be working each night from Sunday night through Friday morning during the overnight period. Lane closures will be present at night for crews to overlay the roadway with hotmix. Lane closures will begin at 7:30 pm each night and should be reopened to traffic by 6 a.m.
US 75 full depth concrete repair, from the Collin County line to the Oklahoma State line. Watch for lane closures on northbound and southbound US 75 as crews will be working each night from Sunday night through Friday morning during the overnight period. Lane closures will be present at night for crews to replace failed concrete sections. Lane closures will begin at 7:30 p.m. each night and should be reopened to traffic by 6 a.m. This work will extend from the Collin-Grayson County line to the Oklahoma State line.
SH 289, in Dorchester at the FM 902 intersection. This project will widen SH 289 on each side of the roadway to allow for the addition of a center left-turn lane. This project will also install traffic signals at this intersection. Watch for shoulder closures and occasional daytime lane closures on the northbound and southbound SH 289 main lanes as well as on FM 902. The new signal light at the SH 289 and FM 902 intersection was activated on Thursday, May 29. The signal has started normal operation, and drivers should pay attention to this new signal as they approach the intersection.
SH 5, in Van Alstyne from Williams Way to Blassingame Avenue. Watch for daytime lane closures on SH 5 as crews work to install a shared use bicycle and pedestrian trail. The trail will follow along SH 5 from the existing trail at Williams Way to Blassingame Avenue, then along Tolson Avenue, then along Main Street where it will connect with Van Alstyne Parkway. Motorists should expect delays during the daytime work hours as flaggers direct traffic through the work zone.
FM 121, from Main Street in Van Alstyne to SH 160. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway to an overall width of 26 feet. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
US 82, from the SH 91 to the Fannin County. Watch for daytime lane closures on the US 82 eastbound and westbound main lanes as crews work to perform pavement repairs and then a pavement overlay on the surface. Motorists should expect delays during the daytime work hours.
US 75 debris pickup, from Collin County line to Oklahoma State line. Watch for mobile lane closures as workers pick up debris from the roadway every Sunday, Tuesday, and Thursday during the nighttime.
US 377 in Tioga, from South of FM 922 to North of Mc Knight Rd. and from Hinton St. to Shawnee Dr. This project will widen US 377 on each side of the roadway to allow for the addition of a center left-turn lane. This project will also install traffic signals at the intersection of US 377 & FM 121 and at the intersection of US 377 & FM 922. Watch for shoulder closures and occasional daytime lane closures on the northbound and southbound US 377 main lanes as well as on FM 922. Motorists should expect delays during the daytime work hours as flaggers direct traffic through the work zone.
Southmayd Rd at Elba Creek, the bridge at Elba Creek was closed beginning June 25. The Contractor demolished the bridge and started replacing it. During the closure, traffic is asked to use Frog Pond Rd & Spalding Rd or Klas Rd & Hazelwood Rd.
FM 901, from US 82 to US 377. Watch for daytime lane closures as maintenance crews perform a level up on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
Fannin County:
Bonham State Park, Park Road 24. Park Road 24 in the Bonham State Park will have daytime lane closures while crews rehabilitate the main road, camping spots and parking lots within the park. Detour routes will be present during construction to allow for the flow of traffic.
FM 68, at the North Sulphur River bridge. FM 68 at the North Sulphur River bridge is closed to through traffic as crews work on and replacing the bridge structure and roadway approaches. During the closure, traffic is asked to use SH 34, SH 11, and SH 78 as the detour route.
FM 2645, from FM 898 to FM 1753. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway to an overall width of 26 feet. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
FM 274, from SH 78 to FM 1753. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway to an overall width of 26 feet. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
FM 274 is closed to thru traffic at the Sandy Creek Bridge in order for the contractor to replace the bridge and approaches. During the closure, traffic is asked to use SH 78 and FM 1753 to detour around the closure.
SH 121 overpass at US 69. The SH 121 overpass at US 69 opened to all traffic on 6/23/2025. Construction crews will continue working on minor items at this location. Motorists should expect delays as there will be daily lane closures through the construction zone.
CR 1202 at Tributary of Brushy Creek. The onsite detour on CR 1202 at Tributary of Brushy Creek has been removed. The new bridge is competed and open to traffic. Traffic is asked to approach the bridge slowly and drive at an appropriate speed through the work zone while crews continue working on finishing the remaining bridge work.
CR 2865 at Sanders Creek Tributary. CR 2865 at Sanders Creek Tributary was closed to traffic on Monday, April 21 to allow for replacement of the bridge. The bridge at Sanders Creek Tributary is completed and opened to traffic. The bridge on CR 2825 at Sanders Creek was closed on June 21 & the Contractor demolished the bridge. Traffic will be required to detour onto CR 2815 & CR 2865 while the bridge structure is being replaced.
FM 68, from SH 78 to FM 271. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway to an overall width of 28 feet. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
SH 78, from US 82 to the Oklahoma State line. Watch for daytime shoulder closures and occasional daytime lane closures as workers install sloped-end treatments on drainage structures and replace bridge rail and guardrail.
SH 34, Watch for daytime lane closures as maintenance crews perform herbicide operation roadway. Motorists should expect delays as they drive through the work zone.
FM 151, from Grayson Co. to US 69. Watch for daytime lane closures as maintenance crews perform overlay operations on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.